(1) The Chairperson of the tenders board shall ascertain that the envelopes are sealed and stamped. He shall open them, quickly check the administrative documents produced by bidders and initial the original copies of the bids and administrative documents.
(2) He shall read out or invite someone to read out the administrative documents and main items of the bids, in particular, the deadlines and, where applicable, the amounts of financial bids and any rebates granted.
(3) Attendance at the bid opening session shall be limited to the representatives of bidders and the number of such representatives per bidder shall be 1 (one) even in case of a group of enterprises.
(4) A bid opening report shall be prepared at the session. The bid opening report
shall indicate the admissibility of bids, their administrative compliance, prices, rebates and deadlines. A copy of an extract of the said report to which shall be appended the attendance sheet signed by all the participants shall be handed to each bidder at their request.
(5) The tenders board’s bid opening report shall, where applicable, specify the composition of the evaluation sub-committee. However, all information on the composition shall remain internal to the board.
(6) The Chairperson of the tenders board shall ensure the safe-keeping of the original copies of all the bids received.
(7) The Chairperson of the tenders board shall certify a copy of each of the bids submitted, which shall be placed at the disposal of the public contracts regulatory body at the close of the bid evaluation session.
(8) For bids to be opened in two stages, a sealed copy of the financial bid shall be forwarded to the public contracts regulatory body for safe-keeping.
(9) Where an administrative bid document is missing or found to be non-compliant during the bid opening session, the bidder concerned shall have 48 (forty-eight) hours to produce or replace the document concerned. However, any bid without bid bond during the bid opening session shall be rejected.
(10) At the end of the bid opening session, all the bids, including those rejected, shall be handed over to the Evaluation Sub-Committee set up by the tenders board. The 39 Evaluation Sub-Committee shall comprise at least 3 (three) members including 1 (one) representative of the Project Owner or the Delegated Project Owner.
Official text
Transcription: Spot-checked
In force from 20-06-2018
Source page 38
The document's transcription was spot-checked against the supplied source; this does not confirm a line-by-line review of every provision.
How Lex Cameroon marks its texts →
Section 92 of the Public Contracts Code/akn/cm/act/decret/2018-06-20/2018-366
Report an error in this text
AI features are in beta
Where an official English or French text exists, we show it; where none does, we give
a translation, clearly marked as one and never presented as the official text. We make
every AI feature as accurate as we can, but it can be wrong and is not legal advice —
always check the cited official text.