SECTION 98

(1) At the end of its work, the Bid Evaluation Sub-committee shall submit an evaluation report to the tenders board. (2) The evaluation report shall be a single document initialled and signed by all the sub-committee members. (3) In case of disagreement, members who do not sign the evaluation report shall express their opinion in a memorandum addressed to the Chairperson of the tenders board with a copy to the Project Owner or the Delegated Project Owner. The Chairperson of the tenders board shall ensure that the said memorandum is attached to the validated evaluation report. (4) The evaluation report shall be presented to the tenders board by the Chairperson of the Evaluation Sub-committee or, as appropriate, by a member of the said Sub-committee duly designated by the Evaluation Sub-committee Chairperson. SUB-SECTION IX AWARD OF PUBLIC CONTRACTS
Official text Spot-checked In force from 20 June 2018 Source page 40

Spot-checked against the official gazette — not yet verified line by line. How Lex Cameroon marks its texts →

A question about this section?

Enter to send · Shift+Enter for a new line

Texte français

ARTICLE 98

Contents

Section 98 of the Public Contracts Code /akn/cm/act/decret/2018-06-20/2018-366
Report an error in this text