Lex Cameroon

Public Contracts Code › Title 2 › Chapter 2 › Section 1

SECTION 41

(1) The Chairperson of the central contracts control board shall notify the Board’s reasoned opinion to the Project Owner or the Delegated Project Owner, the Public Procurement Authority and the public contracts regulatory body as follows: - within 48 (forty-eight) hours with effect from the closing date of deliberations, where the Board expresses no objection to the award; - within 72 (seventy-two) hours with effect from the closing date of deliberations, where the board expresses any other opinion. (2) In case of no objection, the Project Owner or the Delegated Project Owner shall publish the invitation to tender or award the contract and notify his decision to the Chairperson of the board within 5 (five) working days with effect from the date of receipt of the notification of opinion referred to in (1) above.
Official text Spot-checked In force from 20 June 2018 Source page 19

Spot-checked against the official gazette — not yet verified line by line. How Lex Cameroon marks its texts →

A question about this section?

Enter to send · Shift+Enter for a new line

Texte français

ARTICLE 41

Contents

Section 41 of the Public Contracts Code /akn/cm/act/decret/2018-06-20/2018-366
Report an error in this text