Central contracts control boards shall be seised by Project Owners or
Delegated Project Owners depending on the nature of services and shall give an opinion
on:
(a) the tender files prepared by Project Owners or Delegated Project Owners and
examined by tenders boards;
(b) the contract award procedure;
(c) the contract award proposals of tenders boards validated by Project Owners or
Delegated Project Owners;
(d) draft contracts awarded by mutual agreement falling within their remit and any
draft contract amendments.
Official text
Spot-checked
In force from 20 June 2018
Source page 13