(1) The Chairperson of the central contracts control board shall notify the Board’s reasoned opinion to the Project Owner or the Delegated Project Owner, the Public Procurement Authority and the public contracts regulatory body as follows:
-
within 48 (forty-eight) hours with effect from the closing date of deliberations, where the Board expresses no objection to the award;
-
within 72 (seventy-two) hours with effect from the closing date of deliberations, where the board expresses any other opinion.
(2) In case of no objection, the Project Owner or the Delegated Project Owner shall publish the invitation to tender or award the contract and notify his decision to the Chairperson of the board within 5 (five) working days with effect from the date of receipt of the notification of opinion referred to in (1) above.
Official text
Transcription: Spot-checked
In force from 20-06-2018
Source page 19
The document's transcription was spot-checked against the supplied source; this does not confirm a line-by-line review of every provision.
How Lex Cameroon marks its texts →