Decree No. 2018/355 on common rules applicable to contracts by public corporations › Chapter 8

SECTION 95

(1) For multiple-phase contracts, the final bond for each phase shall be put up within 20 (twenty) days following receipt of the Notice to Proceed with the phase concerned. (2) The contract registration and bond shall be done in instalments. VII. Security
Official text Spot-checked In force from 12 June 2018 Source page 28