(1) For each file to be examined, the Chairperson of the central contracts
control board shall select an expert, on account of his expertise in the area concerned by
the project, from a list drawn up and regularly updated by the public contracts regulatory
body.
(2) The expert shall examine the technical aspects of the documents received
from the Project Owner or the Delegated Project Owner and prepare and submit a report
to the Contracts Control Board within 5 (five) working days. He shall answer questions
from members of the central contracts control board, but may under no circumstances
take part in deliberations.