SECTION 183

Today
Notwithstanding the provisions of Article 182 of this code, the Project Owner or the Delegated Project Owner may, in case of force majeure and after obtaining the opinion of the Authority in charge of public contracts, terminate a contract without the Administration’s contracting partner being liable, and without prejudice to damages that he may claim. Paragraph 3 Consequences of Termination
Official text Transcription: Spot-checked In force from 20-06-2018 Source page 69

The document's transcription was spot-checked against the supplied source; this does not confirm a line-by-line review of every provision. How Lex Cameroon marks its texts →

Litigations and sanctions Litigations during the execution phase sub-section i termination

A question about this section?

Enter to send · Shift+Enter for a new line

Texte français

Official text

ARTICLE 183