(1) Where the Project Owner or the Delegated Project Owner disagrees
with a proposal made by the tenders board, he shall be bound to request another review
of the file and state his reservations within 3 (three) working days from the date of receipt
of the proposal made by the relevant tenders board.
(2) The chairperson of the tenders board shall communicate the findings of the
68
new review to the relevant Project Owner.
(3) Where the disagreement persists, the Project Owner or the Delegated Project
Owner shall refer the matter to the Authority in charge of public contracts.
(4) The Authority in charge of public contracts may seek the opinion of the public
contracts regulatory body which shall, in this case, respond within 7 (seven) days.
(5) Notification of the contract shall be subject to the decision of the Authority in
charge of public contracts.
SUB-SECTION III
DISAGREEMENTS BETWEEN THE CENTRAL CONTRACTS CONTROL BOARD AND
THE PROJECT OWNER OR THE DELEGATED PROJECT OWNER
Official text
Spot-checked
In force from 20 June 2018
Source page 67