(1) Any contract shall be subject to a single document written out on both sides of the paper, to which the contract documents shall be attached.
(2) Every contract shall be published, notified, and the Notice to Proceed issued to the contracting partner before the start of contract execution.
(3) Any claim concerning work for which the Notice to Proceed was not issued before the start of contract execution shall be inadmissible.
(4) An initial advance payment, whose amount shall be capped at 20% for works and supply contracts, and 30% for supply contracts, may be granted to the contractor upon request, provided that contractor meets all the required conditions and guarantees.
Official text
Transcription: Spot-checked
In force from 12-06-2018
Source page 23
The document's transcription was spot-checked against the supplied source; this does not confirm a line-by-line review of every provision.
How Lex Cameroon marks its texts →
A question about this section?
Texte français
Lex Cameroon does not hold a French version of this provision. You can read an unofficial machine translation — for understanding only, never to quote.