Notwithstanding the provisions of Article 182 of this code, the Project Owner or the Delegated Project Owner may, in case of force majeure and after obtaining the opinion of the Authority in charge of public contracts, terminate a contract without the Administration’s contracting partner being liable, and without prejudice to damages that he may claim.
Paragraph 3 Consequences of Termination
Official text
Transcription: Spot-checked
In force from 20-06-2018
Source page 69
The document's transcription was spot-checked against the supplied source; this does not confirm a line-by-line review of every provision.