A lessee with no right to renew for whatever reason may nevertheless be reimbursed for the cost
of constructions and improvements carried out on the premises with the authorisation of the
lessor.
Where there is no agreement between the parties, the lessee may bring an action before the
competent court as soon as the lease for a specified duration expires, or as soon as the notice to
quit is given with respect to a lease for an unspecified duration.
Official translation
Spot-checked
In force from 17 April 1997
Source page 35