The execution of public contracts shall be monitored by the Project Owner
or the Delegated Project Owner through the Contract Manager, the Contract Engineer,
and the Project Manager, where necessary.
20
To this end, the Project Owner shall;
(a) designate the Contract Manager and the Contract Engineer, and provide them
with the appropriate means for a proper discharge of their duties;
(b) sign administrative orders to commence service delivery;
(c) sign administrative orders having an incidence on costs, time limits and
objectives under the conditions specified in the general administrative
clauses;
(d) designate a representative to chair the Service Acceptance Committee;
(e) order payment on account;
(f) terminate contracts after formal notice, where necessary;
(g) ensure the drafting of the contract execution completion report.