Lex Cameroon

Public Contracts Code › Title 4 › Chapter 3 › Section 4

SECTION 169

(1) The penalties for exceeding the contractual period notwithstanding, the contract may provide for specific penalties for non-compliance with the technical and safety measures. (2) In any case, the cumulative amount of penalties shall not exceed 10% (ten per cent) of the tax-inclusive amount of the initial contract and its amendments, as applicable, under pain of termination.
Official text Spot-checked In force from 20 June 2018 Source page 65

Spot-checked against the official gazette — not yet verified line by line. How Lex Cameroon marks its texts →

A question about this section?

Enter to send · Shift+Enter for a new line

Texte français

ARTICLE 169

Contents

Section 169 of the Public Contracts Code /akn/cm/act/decret/2018-06-20/2018-366
Report an error in this text