(1) Payments on account must be made monthly or at an interval agreed
between the Project Manager and the Project Owner’s representative.
(2) Payments on account may be spread over the contract period, according to
64
periodic deadlines, or depending on technical execution phases, as specified under the
contract.
(3) Payments on account shall be made no later than ninety (90) working days
from the date the reports giving entitlement to payment are forwarded to the competent
accountant.
(4) General or special administrative clauses shall specify the periods allowed for
the Project Officer or, where applicable, the Project Manager, to produce the documents
giving entitlement to payment on account.
(5) In any case, the period for making payments on account may not exceed 60
(sixty) working days from the date of forwarding the draft partial payment document to
the Project Manager, provided the document does not require correction.