SECTION 157 — (1) Acceptance or follow-up and technical validation must lead to the onthe-spot signing of the acceptance report which shall state whether or not acceptance was decided and, where applicable, mention the reservations to be lifted, together with deadlines, before deciding on the said acceptance.
(2) To be valid, the acceptance report must be signed by at least 2/3 (two thirds)
of members, including the chairperson.
(3) The chairperson, members and rapporteurs shall receive an acceptance and
technical validation allowance determined by decision of the Project Owner or the
Delegated Project Owner.
(4) The allowance shall be charged to the budget of the Project Owner or the
Delegated Project Owner.