SECTION 123

(1) Each contract shall be a single document printed on the first side of the page. (2) Public contracts and their amendments shall be notified by the Project Owner or the Delegated Project Owner. (3) Each public contract shall be notified before commencement of execution. 50 (4) Consequently, any claim regarding the supply of goods or services prior to contract notification shall be inadmissible. (5) Upon notification of the contract to the allotee, the Project Owner or the Delegated Project Owner shall have 15 (fifteen) calendar days within which to issue the administrative order to commence service delivery. (6) The Project Owner or the Delegated Project Owner shall send a copy of the service order to commence service delivery to the public contracts regulatory body and to the Ministry in charge of public contracts within 7 (seven) calendar days, with effect from the date of its notification.
Official text Spot-checked In force from 20 June 2018 Source page 49

Spot-checked against the official gazette — not yet verified line by line. How Lex Cameroon marks its texts →

A question about this section?

Enter to send · Shift+Enter for a new line

Texte français

ARTICLE 123

Contents

Section 123 of the Public Contracts Code /akn/cm/act/decret/2018-06-20/2018-366
Report an error in this text