(1) At the end of the technical bid evaluation phase, where bid opening comprises two (2) stages, the Project Owner shall be required to inform bidders of the technical bid evaluation results prior to the opening of the financial bids.
(2) At the end of technical bid evaluation, unsuccessful bidders may file a petition with the Petitions Review Committee with copy to the Project Owner or the Delegated Project Owner, the chairperson of the relevant tenders board, and the Authority in charge of public contracts. 67
(3) The petition shall be filed within 3 (three) working days after the financial bid opening session.
Official text
Transcription: Spot-checked
In force from 20-06-2018
Source page 66
The document's transcription was spot-checked against the supplied source; this does not confirm a line-by-line review of every provision.
How Lex Cameroon marks its texts →