(1) Each contract shall be a single document printed on the first side of the page.
(2) Public contracts and their amendments shall be notified by the Project Owner or the Delegated Project Owner.
(3) Each public contract shall be notified before commencement of execution. 50
(4) Consequently, any claim regarding the supply of goods or services prior to contract notification shall be inadmissible.
(5) Upon notification of the contract to the allotee, the Project Owner or the Delegated Project Owner shall have 15 (fifteen) calendar days within which to issue the administrative order to commence service delivery.
(6) The Project Owner or the Delegated Project Owner shall send a copy of the service order to commence service delivery to the public contracts regulatory body and to the Ministry in charge of public contracts within 7 (seven) calendar days, with effect from the date of its notification.
Official text
Transcription: Spot-checked
In force from 20-06-2018
Source page 49
The document's transcription was spot-checked against the supplied source; this does not confirm a line-by-line review of every provision.
How Lex Cameroon marks its texts →