(1) Where the Project Owner cannot determine in advance the volume and the rate of supply orders or routine services required for his needs, he may resort to a framework agreement.
(2) Framework agreements shall be contracts concluded by one or more Project Owners with one or more service providers in order to lay down rules relating to the purchase orders to be issued, or the provisions governing subsequent framework agreements to be concluded over a given period, particularly regarding prices and, where necessary, the quantities envisaged.
(3) Framework agreements may not exceed 3 (three) years.
(4) Where the framework agreement is signed for a period of more than 12 (twelve) months, and where the framework agreement clearly so provides, each of the contracting parties shall have the latitude to request, on the dates fixed by them, the revision of prices by applying the price revision formula contained therein, or terminate the contract where the application of the price revision formula may to lead to a unit price variation of more than 25%.
(5) The use of framework agreements shall apply only to supplies or recurrent services as well as maintenance and renovation works.
Official text
Transcription: Spot-checked
In force from 20-06-2018
Source page 29
The document's transcription was spot-checked against the supplied source; this does not confirm a line-by-line review of every provision.
How Lex Cameroon marks its texts →
Section 65 of the Public Contracts Code/akn/cm/act/decret/2018-06-20/2018-366
Report an error in this text
AI features are in beta
Where an official English or French text exists, we show it; where none does, we give
a translation, clearly marked as one and never presented as the official text. We make
every AI feature as accurate as we can, but it can be wrong and is not legal advice —
always check the cited official text.