(1) The Project Owner or the Delegated Project Owner shall be bound to take
all necessary measures to make available the work site before notifying the contract
concerned. He must show proof, where appropriate, of the effective existence of the
declaration of public utility, the expropriation decree, the transfer instrument or any other
legal or administrative instrument showing proof of the availability of the site.
28
(2) The Project Owner or the Delegated Project Owner shall be bound to ensure
the availability of funding before launching bidding. This shall entail attesting, as the case
may be, to the budget allocation, the effective expenditure authorization, and the entry
into force of the funding agreement.
(3) For recurrent services or projects whose effective commencement date is
incompatible with prior adoption of the budget of the corresponding financial year, related
consultations may be launched before the adoption of the said budget.
(4) In the cases referred to in (3) above, the notification of the contract shall be
subject to the existence of evidence of funding and site availability, where applicable.